(2/1/23) Complete
(1/10/23) Work starting this week
(12/13/22) Project approved, will start in January 2023.
(12/12/22) Sent for rebid
(3/14/22) Sent for rebid
(11/15/21) RFQ Sent for adding camera cluster
(1/10/23) Complete
(12/20/22) Project underway
(12/7/22) Project Approved
(11/9/22) Sent for RFQ
(11/9/22) Complete
(7/27/22) Centerpoint construction timeline is mid to late September 2022.
(6/1/22) Board approved streetlights on Post Meadow
(10/6/22) Done(8/29/22) Transformer pole installed, CCTV and light poles have been installed, waiting Centerpoint Meter(7/27/22) Centerpoint transformer install will be approximately week of 8/18/22. Electrical and then camera installation can happen after that. (6/1/22) Board approved project(3/14/22) Sent for bid
(8/29/22) Completed (8/11/22) Electrical work complete, waiting on Centerpoint to install meter(7/27/22) Electrical work should start this week(6/1/22) Board approved project(3/14/22) Sent for bid
Running a holiday sale or weekly special? Definitely promote it here to get customers excited about getting a sweet deal.
(8/11/22) Complete
(7/27/22) Electrician has been requested to fix the out outlet
(8/11/22) Complete(7/27/22) Electrician has been requested to fix the out landscape lights on Windsand
(6/1/22) Completed (4/27/22) Contractor has started demo (3/29/22) Bid approved by board
(4/27/22) Delivered (1/18/22) Order placed, anticipated delivery is May 2022 (11/15/21) RFQ Sent for replacing pool furniture
(4/7/22) Complete (3/22/22) Bid accepted and work has started (11/15/21) The board has requested Spectrum to re bid this (4/5/21) Currently bidding to have our mailbox clusters cleaned and repainted
(4/5/22) Completed (3/22/22) RFQ accepted (3/7/22) Request an RFQ to repaint the lettering on the monuments
(3/29/22) Completed and operational (3/22/22) Centerpoint updated schedule, install late March 2022 (1/18/22) On Centerpoint construction schedule, estimated install is mid March 2022 (12/7/21) Contract awarded (11/20/21) The board sent a RFQ to Centerpoint
(3/10/22) Complete. (1/18/22) Work is 50% complete, waiting on Centerpoint to install meter (12/7/21) Contract awarded (11/15/21) RFQ Sent for adding camera cluster
(3/10/22) Complete (1/18/22) Work is 50% complete, waiting on Centerpoint to install meter (12/7/21) Contract awarded (11/15/21) RFQ Sent for adding camera cluster
(2/22/22) Complete (1/18/22) Scheduled to be completed today (12/6/21) Contract awarded. Completion will be done after Holiday Decorations are removed in January (11/29/21) RFQ Sent for pressure washing all monuments
(2/22/22) Completed
(1/18/22) RFQ Sent for replacing Park Sign at the Rec Center
(12/9/21) Complete
(11/29/21) Contract awarded. Estimated completion 1-2 weeks
(2/2/22) Complete and operational
(1/18/22) Work is 50% complete, waiting on Brivo to transfer account
(12/1/21) In order to support Swim at Your Own Risk in 2022, the board signed a contract to expand the electronic door locks on all doors at the pool
(1/18/22) Complete
(12/9/21) Work Started
(12/1/21) In order to support Swim at Your Own Risk in 2022, the board signed a contract to expand the security cameras at the pool
(12/9/21) Complete
(11/29/21) Contract awarded. Estimated completion 1-2 weeks
(12/9/21) Complete
(12/2/21) Almost complete, punch list work in progress
(11/15/21) Ongoing
(9/21/21) The board has signed a contract to trim the HOA owned trees within the community. Estimated start date is late October 2021.
(11/19/21) Complete
(11/15/21) Ongoing
(9/21/21) The board has signed a contract to replace the pool equipment and construct a shelter over the pool equipment to prolong life of said new equipment. Construction is estimated to start in November
(9/27/21) Work Completed
(9/21/21) Work is still outstanding
(8/3/21) Contractor has been selected
(6/23/21) Single vehicle accident at the Windstone South Monument has caused damage. The driver admitted fault and driver's insurance has confirmed responsibility. Contractors have been contacted to bid repair. Insurance claim has been filed with driver's insurance.
(9/21/21) Completed
(8/3/21) Project should be completed end of August.
(6/13/21) Waiting on Centerpoint to put on construction schedule.
(5/24/21) Check has been mailed to Centerpoint, waiting on Centerpoint to put on construction schedule.(5/17/21) No update, waiting on Centerpoint to put on construction schedule.
(5/2/21) Waiting on Centerpoint for scheduling. View Proposed drawing for light locations HERE
(4/22/21) The board has awarded a contract to Centerpoint for street lights on Windystone. The contract includes 35 LED lights mounted to 30' poles. This should provide adequate lighting for Windystone at night. A big win for the community.
(4/5/21) Currently requesting Centerpoint for a bid on street lights along Windystone
(9/21/21) Completed
(8/3/21) Contractor has submitted bid and board has approved. Work to start next week.
(9/21/21) Completed
(8/3/21) Project underway, to be completed soon
(6/23/21) Work is underway
(5/24/21) Board has reached out to County for an update
(4/5/21) New Traffic Light at Windstone Manor and Fry. Entrance to Windstone Colony South. Anticipated installation in Q2 of 2021 **This project is being managed by Harris County**
(5/28/21) Complete and Operational
(5/24/21) Weather Delays, should be done this week(5/17/21) Contract to replace pole has been awarded and should be completed this week, weather depending. Insurance claim has been filed. (5/7/21) Light pole was struck and damaged by motorist
(5/28/21) Work Complete
(5/24/21) Work is underway, should be completed this week(5/17/21) Work is underway(5/4/21) Work has started. Expected to take two weeks.(4/22/21) Insurance claim has been accepted, Contractor quote has been accepted. The board is taking the time to do some upgrades along with the Insurance covered repairs. Repairs should take 2 weeks, starting 5/5/21. Repairs/Upgrades include new water fountains, new showers, new countertops and sinks, repainting, and more!(4/5/21) Plumber has completed repairs. Currently working with insurance and bidding General Contractors to repair damage.
(5/28/21) Complete and operational
(5/24/21) Board cancelled contract with Electrician. A new contract with our new Pool Management company to replace these lights has been agreed to.(5/17/21) Still waiting(4/22/21) Still waiting for Lights from Manufacturer(4/5/21) Current pool lights have malfunctioned, replacing all pool lights with safer low voltage LED pool lights. Anticipated installation in May 2021.
(5/17/21) Work is completed (4/22/21) Many plants along with parts of the irrigation system have been damaged due to the Freeze event. The board has directed our landscaping contractor to repair the irrigation and begin replacing the landscaping where it makes sense. Starting with the front entrances.
(5/17/21) Work completed(5/2/21) Work has started, 30% complete(4/22/21) Work should start 4/26/21. (4/5/21) Fence replacement contract has been awarded. The 770' section of fence north of Windstone Manor along Fry Rd will be replaced. Homeowners in the area will be notified when we have firm installation dates.
(5/2/21) Complete and operational
(5/17/21) Work has completed(5/2/21) Work has started, Pool fence has been repainted, cul de sacs are next(4/22/21) Work should start at the pool fence 4/22/21. The cul de sacs will follow after pool fence. Some repair work needs to be done before painting. (4/5/21) Our Reserve study directs us to paint all of the metal fencing this year, this includes metal fencing at the end of some cul-de-sacs as well as the metal fence around the pool
(5/2/21) Complete and operational
(5/2/21) Complete and operational
Speedy the turtle (the turtle fountain in the kids pool) is being given a fresh coat of paint
The replacement of the aging roof and trim on the pool house has been completed.
There is now WIFI available for guest use while at the Pool
All new access control system for the gate at the pool. Look for information coming soon on how to get a Pool Key Fob.
All new CCTV system installed at Windystone and Wind Trace
All new CCTV system installed at Windstone South Park